WPS and payroll in the UAE: the due date and the 85% rule
UAE wages are due on the 1st of each month through WPS, 85% on time. The day-by-day penalties, exemptions, free zone rules and unemployment insurance.

Answer in brief
Every MOHRE-registered company pays wages through the Wage Protection System. Since 1 June 2026, wages are due on the 1st of the next month, with at least 85% paid by then (Ministerial Resolution No. 340 of 2026). From the fifth day after the due date, MOHRE stops new work permits; fines for repeat violations and labour disputes follow. Free zones set their own WPS rules. Checked 12 November 2026.
- Ministerial Resolution No. 340 of 2026 replaced Ministerial Resolution No. 598 of 2022 on 1 June 2026: one due date on the 1st, an 85% threshold, and no 15-day window or 30-day grace for new joiners
- Late payroll blocks your next hire: new work permits are suspended from the fifth day after the due date
- Unemployment insurance, worker protection insurance and, for Emirati staff, the AED 6,000 minimum wage and pension contributions sit on the same payroll
On this page (18)
The WPS rule since 1 June 2026: one due date and 85% paid on time
Every establishment registered with the Ministry of Human Resources and Emiratisation (MOHRE) must pay its workers through the Wage Protection System (WPS), the electronic salary-transfer system MOHRE monitors. Wages for each month are due on the first day of the next Gregorian month, and any later payment counts as a delay (Article 1(1) of Ministerial Resolution No. 340 of 2026). Wages for October are due on 1 November.
You count as compliant if, by the due date, you transfer at least 85% of the total wages due to your workers (Article 2(1)). A worker who receives at least 85% is not treated as unpaid where the difference is a lawful deduction under Article 25 of the labour law (Article 2(2)). The rest of the wage is still owed: the 85% test decides when MOHRE's measures start, not how much you must pay.
The resolution was issued on 12 May 2026 and has applied since 1 June 2026 (Article 8). It repealed Ministerial Resolution No. 598 of 2022 (Article 7). Three features of the old rules no longer apply:
| Rule | Ministerial Resolution No. 598 of 2022 (repealed) | Ministerial Resolution No. 340 of 2026 |
|---|---|---|
| Due date | First day of the month after the payday in the contract | First day of each Gregorian month, for every employer |
| When a payment is late | After 15 days | Any payment after the due date |
| Threshold | More than 80% | At least 85% |
| New employees | Excluded for 30 days | No grace period |
The repealed figures come from the 2022 resolution. Morgan Lewis's note of 22 May 2026 reads the change the same way (Morgan Lewis).
MOHRE's own WPS guidance page, as of 26 October 2026, still says wages are paid at the time agreed in the employment contract, while listing the 2026 resolution as the law. The resolution wins.
The labour law itself requires wages to be paid on their due dates through the systems MOHRE approves (Article 22(2) of Federal Decree-Law No. 33 of 2021). Its Executive Regulation lets MOHRE refuse, not renew or cancel work permits where WPS is not complied with (Article 7(4)(c)).
See our update on MOHRE Resolution No. 340 of 2026 and the salary due date.
Who must use WPS: mainland, free zone, DIFC and ADGM companies
Mainland. Every establishment registered with MOHRE (Article 1(2) of the resolution; Executive Regulation, Article 16(1)(b)). u.ae's wages page (updated 14 October 2026) says payment goes through banks, exchange houses or financial institutions authorised by the Central Bank of the UAE.
Free zones. A free zone employer follows its zone's WPS rules. Two zones publish theirs:
| Zone | Rule | Source |
|---|---|---|
| DMCC | Every employer registers all employees holding an active or expired employment visa or permanent identity card; shareholders are not obliged. Register a new employee immediately after the company employment card is issued. Pay only in AED, and do not deduct bank charges from wages. Each employee must receive at least 80% of the expected salary | DMCC WPS guideline, version 4, 22 May 2025 |
| JAFZA | All JAFZA-registered businesses must comply with the UAE WPS, required since 2012 | JAFZA WPS guide |
DMCC's 80% per employee and MOHRE's 85% of total wages are separate regimes, both current as of 26 October 2026. In another zone, ask the zone for its WPS rules in writing; we did not read them. The zone profiles for DMCC and JAFZA cover setup there.
DIFC and ADGM. We did not read their payroll rules. Ask the DIFC Authority or the ADGM Registration Authority; the DIFC profile and ADGM profile cover those centres.
Workers and employers outside WPS
Article 4 of the resolution excludes these cases from the WPS measures:
- a worker whose wage claim has gone to court or to an executive instrument, within the limits of the claim
- a worker under an absconding report
- a worker whose liberty is restricted, or on approved unpaid leave, once MOHRE is notified
- seafarers, on request
- foreign workers of a foreign establishment or its UAE branch paid outside the UAE, on the establishment's request and with the workers' approval
- workers on mission permits of up to three months
- fishing boats and public taxis owned by individual UAE citizens
- banks and financial institutions, and places of worship
The foreign-establishment case is an exemption a UAE branch requests, not a default; see the foreign company branch route.
What happens if salary is late in the UAE: MOHRE's day-by-day measures
Annex 1 of Ministerial Resolution No. 340 of 2026 sets the measures by the number of days after the due date.
| When | Measure | Who it applies to |
|---|---|---|
| From the due date | Electronic monitoring | All establishments |
| From the second day after | Notifications and alerts | Non-compliant establishments |
| Fifth day after | New work permits suspended | Non-compliant establishments |
| Eleventh day after | Administrative fine under Cabinet Resolution No. 21 of 2020 and reclassification into the Third Category under Ministerial Resolution No. 209 of 2022 | Non-compliant establishments that repeat the violation within six months |
| Sixteenth day after | Automatic individual or collective labour dispute, and permit suspension | Establishments with 25 or more workers; or same-owner groups with 25 or more unpaid workers in construction, transport and storage, security, cleaning, recruitment agencies and domestic worker offices |
| Twenty-first day after | Executive instrument (fewer than 50 workers) or collective labour dispute (50 or more); precautionary attachment; travel ban on the person in charge; referral to the Public Prosecution for more than 50 workers with a repeat within two consecutive months | As stated in each measure |
The resolution counts days "following the due date" and does not say whether they are calendar or working days. Article 1 makes the first of the month the due date and treats any later payment as a delay; the text we read says nothing about a 1st that falls on a weekend or public holiday, so ask MOHRE rather than assuming a later date (resolution read 12 November 2026).
The annex's targeted column for day 21 names establishments with 50 or more workers that repeat the violation, same-owner groups with 50 or more unpaid workers in the listed sectors, and any case that risks the stability of the labour market regardless of size; ask MOHRE whether a smaller establishment is targeted.
Cabinet Resolution No. 21 of 2020 fines non-payment of wages through WPS AED 1,000 per worker, up to AED 20,000 (Article 3, row 7, UAE Legislation portal English text, last updated 15 April 2022). MOHRE has not said that this is the row it applies on day eleven; ask MOHRE.
The trap for a growing company is day five: late payroll stops the work permit for your next hire until wages are back in order. The compliance calendar holds the 1st-of-month due date.
How to register for WPS and run payroll, step by step
| Step | What you do | Authority or document |
|---|---|---|
| 1 | Register the establishment with MOHRE (labour file and establishment card) | MOHRE; see the employee visas guide |
| 2 | Choose a WPS agent: a bank, exchange house or financial institution authorised by the Central Bank of the UAE | u.ae wages page; your company account first, see corporate account readiness |
| 3 | Register each employee with the agent, using the employee's bank account or the agent's card | WPS agent |
| 4 | Each month, send the salary file so that at least 85% of total wages arrives by the 1st | Resolution, Articles 1 and 2 |
| 5 | Keep the documents and data that prove payment, and submit them when asked | Resolution, Article 1(3) |
| 6 | Notify MOHRE, with documents, of any worker who falls under an Article 4 exclusion | Resolution, Article 4 |
| 7 | If a payroll provider pays for you, give MOHRE the provider's details and the delegation contract | Resolution, Article 5(1) |
Delegating payroll does not move the risk: the establishment stays responsible for paying wages on their due dates (Article 5(2)). Adviser observation: have one person prepare the salary file and another approve it, and log every rejected file and its fix.
Wages may be paid in AED or in another currency if agreed (labour law, Article 22(3); u.ae), unless your zone requires AED, as DMCC does. u.ae says the labour law sets no minimum salary. The wage in the salary file should match the wage in the registered contract; see the employment contracts guide.
Unemployment insurance: who must subscribe, and the fines
Unemployment insurance (ILOE) is compulsory for employees in the federal government and the private sector, and the worker pays the premium (u.ae job-loss insurance page, read 12 November 2026). Not subscribing carries an AED 400 fine. For unpaid premiums MOHRE and the Dubai government portal say AED 200, while u.ae says AED 400. Premiums, exemptions, benefits and the full fines wording are in the ILOE and statutory cost guide.
Worker protection insurance or the AED 3,000 guarantee
For each worker you need either a bank guarantee of at least AED 3,000 or a worker protection insurance policy, under Ministerial Resolution No. 318 of 2022 as described on u.ae's worker insurance page (updated 7 August 2025).
| Worker type | Premium per certificate |
|---|---|
| Skilled worker | AED 137.50 |
| Low-skilled worker | AED 180 |
| Worker of a high-risk establishment not compliant with WPS | AED 250 |
| Domestic worker | AED 105 |
The certificate is valid for 30 months and covers up to AED 20,000 per worker: unpaid wages for up to the last 120 days, end-of-service benefits, repatriation and work-injury treatment. If the insurer pays and you do not repay it, MOHRE suspends your file and freezes new work permits. Late payroll can also raise this cost: the AED 250 rate is listed for high-risk establishments not compliant with WPS.
Payroll for Emirati staff: minimum wage and pension
Minimum wage. MOHRE set a minimum of AED 6,000 a month for Emiratis in the private sector from 1 January 2026, for new, renewed or amended work permits (MOHRE, 31 December 2025). Existing staff had to be adjusted by 30 June 2026. From 1 July 2026, an Emirati paid less does not count towards your Emiratisation target and new work permits are suspended. The targets are on the employee visas guide.
Pension. Emirati staff are registered with the General Pension and Social Security Authority (GPSSA), and contributions are payroll deductions and employer costs. GPSSA's explainer of the federal pension laws gives two rate sets:
| Law | Total | Employee | Private-sector employer | Government |
|---|---|---|---|---|
| Federal Law No. 7 of 1999 | 20% | 5% | 12.5% | 2.5% |
| Federal Law No. 57 of 2023 | 26% | 11% | 15% | 2.5% of the employer's 15% when the contribution salary is under AED 20,000 |
Both laws exclude the government and private sectors in Abu Dhabi and the government sector in Sharjah. Ask GPSSA which law covers each Emirati employee, and the Abu Dhabi Pension Fund (rules not read) for staff in Abu Dhabi. u.ae's page on Emirati employment (updated 15 October 2026) says you must register an Emirati with the pension system and start contributing within a month of the work permit being issued.
See our updates on the Emirati minimum wage in the private sector and on the Emiratisation 2026 targets and contributions.
Worked example: a late June 2026 payroll for 10 staff
A mainland company has 10 employees and total wages of AED 80,000 for June 2026. The due date is 1 July 2026.
| Line | Arithmetic | Amount |
|---|---|---|
| 85% of total wages | AED 80,000 × 0.85 | AED 68,000 |
| Paid by 1 July | AED 60,000 | |
| Share paid | AED 60,000 ÷ AED 80,000 | 75% |
| Shortfall to reach 85% | AED 68,000 − AED 60,000 | AED 8,000 |
| Still owed to staff in full | AED 80,000 − AED 60,000 | AED 20,000 |
At 75% the company is not compliant. Counting the day after the due date as the first day (our count), the measures fall on these dates:
| Measure | Date |
|---|---|
| Alerts | From 3 July 2026 |
| New work permits suspended | 6 July 2026 |
| Administrative fine and Third Category, if the company repeats the violation within six months | 12 July 2026 |
| Executive instrument, attachment and travel ban, if MOHRE treats the company as targeted (ask MOHRE) | 22 July 2026 |
With 10 workers and no listed sector, the sixteenth-day automatic dispute does not apply. A July hire's work permit stops on 6 July until payroll is fixed.
WPS and payroll checklist
- MOHRE labour file and establishment card first
- WPS agent chosen and every employee registered
- At least 85% of total wages landed by the 1st, the rest following; proof kept
- MOHRE notified of unpaid leave, absconding reports and other Article 4 cases
- Delegation contract filed with MOHRE if a provider pays for you
- Bank guarantee of AED 3,000 or worker protection insurance for each worker
- Unemployment insurance subscription confirmed for each eligible employee
- Emirati staff paid at least AED 6,000 a month and registered with GPSSA within a month of the permit
- Free zone WPS rules in writing from your zone
- Final settlement paid within 14 days of each exit; see the end-of-service guide
When to bring in a payroll or employment specialist
Adviser observation: a company with a handful of staff and one WPS agent can run payroll itself. Bring in a specialist when:
- MOHRE has registered a labour dispute, or you have passed the eleventh day
- your group has 25 or more workers in one of the sectors listed for day sixteen
- you want the Article 4 exemption for a foreign parent's payroll
- you employ staff in DIFC or ADGM
Key facts
| Fact | Value | Applies to | Effective from | Source | Checked |
|---|---|---|---|---|---|
| WPS resolution | Ministerial Resolution No. 340 of 2026; repeals Ministerial Resolution No. 598 of 2022 | Establishments registered with MOHRE | 1 June 2026 | Ministerial Resolution No. 340 of 2026, MOHRE | 12 November 2026 |
| Due date | First day of each Gregorian month for the previous month | As above | 1 June 2026 | Resolution, Article 1(1) | 12 November 2026 |
| Compliance threshold | At least 85% of total wages by the due date | As above | 1 June 2026 | Resolution, Article 2(1) | 12 November 2026 |
| Work permit suspension | Fifth day after the due date | As above | 1 June 2026 | Resolution, Annex 1 | 12 November 2026 |
| Day-eleven fine | Fine under Cabinet Resolution No. 21 of 2020 and Third Category, for a repeat violation within six months | As above | 1 June 2026 | Resolution, Annex 1 | 12 November 2026 |
| Automatic labour dispute | Sixteenth day; 25 or more workers, or listed sectors | As above | 1 June 2026 | Resolution, Annex 1 | 12 November 2026 |
| DMCC threshold | At least 80% of expected salary per employee; AED only | DMCC companies | Guideline of 22 May 2025 | DMCC WPS guideline | 26 October 2026 |
| Unemployment insurance premium | No more than AED 5 a month (basic under AED 16,000); AED 10 (over AED 16,000) | Private-sector and federal employees | As published | u.ae job-loss insurance | 12 November 2026 |
| Unemployment insurance fines | AED 400 not subscribing; AED 200 unpaid premiums per MOHRE, AED 400 per u.ae | Workers | As published | u.ae job-loss insurance and MOHRE news item | 12 November 2026 |
| Worker guarantee | At least AED 3,000 per worker, or insurance | Private-sector employers | Ministerial Resolution No. 318 of 2022 | u.ae worker insurance | 26 October 2026 |
| Worker insurance premium and cover | AED 137.50 skilled; AED 180 low-skilled; AED 250 high-risk and not WPS-compliant; cover up to AED 20,000 per worker | As above | As above | u.ae worker insurance | 26 October 2026 |
| Emirati minimum wage | AED 6,000 a month | Emirati private-sector staff | 1 January 2026 | MOHRE news, 31 December 2025 | 26 October 2026 |
| GPSSA contributions | 26% (11% employee, 15% employer) under Federal Law No. 57 of 2023; 20% under Federal Law No. 7 of 1999 | Emirati staff, except Abu Dhabi and the Sharjah government sector | As published | GPSSA explainer | 26 October 2026 |
For the other statutory payroll costs, including ILOE and gratuity, see the statutory cost of an employee in the UAE.
Sources checked
- Ministerial Resolution No. (0340) of 2026 Concerning the Wage Protection System, Ministry of Human Resources and Emiratisation (PDF): accessed 12 November 2026
- Ministerial Resolution No. 598 of 2022 Regarding the Wages Protection System and its amendment, Ministry of Human Resources and Emiratisation (PDF, repealed): accessed 26 October 2026
- Federal Decree by Law No. (33) of 2021, UAE Legislation portal: accessed 26 October 2026
- Federal Decree-Law No. (33) of 2021 and its amendments, with Cabinet Resolution No. (1) of 2022, Ministry of Human Resources and Emiratisation (PDF): accessed 26 October 2026
- Payment of salaries/wages, u.ae: accessed 26 October 2026
- Wages Protection System, Ministry of Human Resources and Emiratisation: accessed 26 October 2026
- Insurance against job loss, u.ae: accessed 12 November 2026
- Insurance scheme for workers and domestic workers, u.ae: accessed 26 October 2026
- MOHRE raises minimum wage for Emiratis in the private sector to AED 6,000, Ministry of Human Resources and Emiratisation, 31 December 2025: accessed 26 October 2026
- Emiratis' employment in the private sector, u.ae: accessed 26 October 2026
- GPSSA provides breakouts and explanation of UAE federal laws regarding pension, General Pension and Social Security Authority: accessed 26 October 2026
- Electronic Salary Transfer Registration and WPS guideline, version 4, 22 May 2025, DMCC (PDF): accessed 26 October 2026
- Wage Protection System for Jafza companies, JAFZA: accessed 26 October 2026
- UAE tightens wage protection rules with new WPS resolution effective June 2026, Morgan Lewis, 22 May 2026: accessed 26 October 2026
- Cabinet Resolution No. 21 of 2020, Article 3 table of administrative fines, UAE Legislation portal: accessed 26 October 2026
- Not read: Ministerial Resolution No. 209 of 2022; Federal Decree-Law No. 13 of 2022 and Cabinet Resolution No. 97 of 2022; the text of Ministerial Resolution No. 318 of 2022; Abu Dhabi Pension Fund rules; DIFC and ADGM payroll rules; the clauses of Article 25 of the labour law on deductions
Recent rule changes for this guide
Frequently asked questions
No. Article 1(1) of Ministerial Resolution No. 340 of 2026 treats any payment after the 1st as a delay, and the labour law requires the full wage on its due date. The 85% test only decides whether MOHRE treats your establishment as compliant and starts its measures; the unpaid balance remains a wage claim.
Only through the exemption in Article 4 of the resolution. It covers foreign workers of a foreign establishment or its UAE branch who receive their wages outside the UAE, and it needs a request from the establishment and the workers' approval. Without that approval, wages go through WPS like any other employer's.
Yes. u.ae's wages page (updated 14 October 2026) says a worker can contact MOHRE or register a salary complaint. MOHRE decides a claim of AED 50,000 or less, and either party may ask the Court of Appeal to review the decision within 15 working days of notification (labour law, Article 54(2) and (3), as amended). A wage claim in court takes the worker outside WPS for that wage or period (resolution, Article 4).
Not as an establishment registered with MOHRE. The labour law requires wages to be paid through the systems MOHRE approves (Article 22(2)), and u.ae says payment goes through banks, exchange houses or financial institutions authorised by the Central Bank of the UAE.
Related reading
- Operations guideUAE employment contracts: content, MOHRE registration and the legal minimumsUAE employment contracts are fixed-term, with no maximum since 2022. What to include, MOHRE registration, probation up to 6 months, 30 to 90 days' notice.
- Operations guideHiring staff in the UAE: work permit, residence visa, health insurance and EmiratisationUAE employment visa fees: MOHRE permit AED 250 to AED 3,450, GDRFA Dubai and ICP lines, a worked Dubai hire at AED 1,187.50, plus the steps to hire.
- Operations guideUAE gratuity calculation 2026: the 21 and 30 day formula, six worked examples and the savings schemeCalculate UAE end-of-service gratuity: 21 days of basic wage a year for 5 years, then 30, capped at 2 years of wage. Two daily-rate methods, six examples.